COBRAcable commercial operation delayed - updated

The date for when the COBRAcable interconnector starts commercial operation has been updated by the two project owners, Energinet SOV and TenneT TSO. The original date  for commercial operation (6th of February 2019) is not possible. On the basis of the current information available commercial go-live will be delayed until Q3-2019. 

The delay is due to challenges encountered during the laying/installation of the offshore cable by the contractor.